Baggiwood: Sustainable, innovative, comfortable
On December 1, 2023, we moved into a new world of work: where our industrial building once stood on Neugutstrasse in Wallisellen, we have created an innovative new timber structure. You can look back at the construction progress here through photos and videos.
Since December 2023, our new address is: Neugutstrasse 14a, 8304 Wallisellen
Baggiwood new build wins the Best Architects Award 2025
Further details and key facts about the construction
A light spectacle despite the weather debacle (November 30, 2023)
Televista report on the inauguration (November 30, 2023)
Office 2.0 takes shape (November 2023)
Kevin Lieb on the final one percent (October 2023)
The client as an assistant carpenter (June 2023)
Magic, innovation, and enthusiasm: The topping-out ceremony (May 2023)
From the ground to the topping-out tree in 8 weeks (April 2023)
On the construction site with Televista, the Wallisellen television station (April 2023)
Chip by chip... (March 2023)
From Swiss tree to new building (February 2023)
Christmas comes to the construction site (December 2022)
Insulation and concrete work in the basement (October 2022)
Site visit (September 2022)
Excavation (July 2022)
Leveled to the ground (April / May 2022)
Built in 1948 as a factory for Contraves AG
1983 - 2022 Headquarters of A. Baggenstos & Co. AG
Demolished in one week in April / May 2022
Fire alarm (April 20, 2022)
Digging at Baggi's (Early April 2022)
Demolition begins (March 2022)
Time to pack up and go, Baggi's is moving to Wallisellen
Facts & Figures
- Start of construction
March 22 - Hazardous material remediation
March 22 - Demolition / Excavation / Specialized civil engineering
April - June 22 - Sewer relocation
June / July 22 - Structural shell (masonry)
August 22 - Structural shell (timber construction)
February 23 - Building watertight
May 23 - Interior finishing
May 23 - Installations
August 23 - Ready for move-in
December 1, 23